Wallmark installed acoustic barriers at the Lancaster Solar Facility for European Energy in northern Victoria.
Case Study

Lancaster Solar Acoustic Barriers

Client: European Energy
Location: Lancaster, Victoria
Scope: Design, construction and certification of acoustic barriers
Date of Completion: January 2026

01

Results at a Glance

  • Acoustic barriers delivered for multiple inverter locations across a 106 MW solar facility
  • Designed to support compliance with operational noise and environmental planning requirements
  • Durable Corten steel acoustic barrier system engineered for long-term renewable energy infrastructure
  • Integrated with construction sequencing while maintaining site access throughout delivery

02

Client Overview

The Lancaster Solar Facility is a utility-scale renewable energy project developed by European Energy near Kyabram in northern Victoria. The 106 MW solar farm forms part of European Energy’s expanding Australian renewable energy portfolio developed to supply the National Electricity Market. Renewable energy generated by the facility will support Apple’s energy commitments in Australia under a power purchase agreement.

Large-scale solar facilities rely on multiple inverter stations distributed throughout the site, each generating operational noise that must be managed to satisfy environmental planning requirements while maintaining safe access for construction, maintenance and future operations.

Wallmark was engaged to design, construct and certify acoustic barriers for multiple inverter locations, delivering a durable solution that integrated with the broader renewable energy infrastructure while supporting long-term operational performance.

03

Engineering Solution

The project required a series of purpose-designed acoustic barriers strategically positioned around inverter locations throughout the solar facility.

A Corten steel acoustic barrier system was selected to provide a robust, low-maintenance solution suited to the demanding operating conditions of utility-scale renewable energy infrastructure. The barriers were engineered to integrate with the site’s layout while accommodating construction sequencing and maintaining access for installation, commissioning and ongoing maintenance activities.

Wallmark completed the design, construction and certification of the acoustic barriers, delivering infrastructure that supports compliance with General Environmental Duty (GED) planning requirements while providing reliable long-term acoustic performance.

04

Project Outcomes

The completed acoustic barriers now form part of the operational infrastructure supporting one of Victoria’s significant renewable energy developments.

By delivering certified acoustic barriers across multiple inverter locations, Wallmark helped the project satisfy operational noise management requirements while providing a durable solution designed for the long-term demands of utility-scale solar generation.

As renewable energy developments continue to expand across Australia, projects such as Lancaster demonstrate the importance of integrating acoustic infrastructure into renewable energy facilities to support environmental compliance, operational performance and long-term asset reliability.

Smart Wall Solutions for Commercial and Civil projects

Wallmark is at the forefront of providing elegant and cost-effective acoustic solutions for commercial, civil, and industrial settings. Tailored for professionals like architects, builders, developers, and business owners, Wallmark’s innovative SMART soundproof noise walls blend functionality with finesse. This system not only promises significant noise reduction, cost savings, and time efficiency but does so with an eye for contemporary design.

With a track record of quality installations, Wallmark’s solutions are designed to meet the dual demands of aesthetics and performance, ensuring your project stands out for all the right reasons.

Contact Us

Fill in the form below and our team will contact you for assistance with your civil infrastructure solution

  • This field is for validation purposes and should be left unchanged.
  • Max. file size: 128 MB.
  • Max. file size: 128 MB.
  • Max. file size: 128 MB.